Aaj English TV

Thursday, March 28, 2024  
18 Ramadan 1445  

Rs12.5b for Karachi’s ongoing mega projects

No new schemes have been proposed for financial year 2023-24
A general view of the British era Empress Market building is seen after the removal of surrounding encroachments on the order of Supreme Court in Karachi, Pakistan on January 30, 2019. Reuters
A general view of the British era Empress Market building is seen after the removal of surrounding encroachments on the order of Supreme Court in Karachi, Pakistan on January 30, 2019. Reuters

The Sindh government has allocated Rs12.5 billion under the mega schemes package for Karachi in the financial year 2023-24 budget.

Within this budget, as many as 20 ongoing mega schemes have been identified to receive financial support. While no new schemes have been proposed for the upcoming fiscal year, the focus remains on ensuring the timely completion of the existing projects.

The primary areas of concern addressed by these ongoing schemes include the rehabilitation of Karachi’s roads and drainage system.

The importance of well-maintained roads cannot be overstated in a city as vast and populous as Karachi. Many are of the view that the rehabilitation efforts will not only improve the overall connectivity and ease of transportation but also contribute to reducing traffic congestion and enhancing road safety.

Furthermore, the drainage system in Karachi has long been a matter of concern, especially during monsoon seasons when heavy rainfall often leads to flooding in low-lying areas.

The allocated funds will be utilised to enhance the existing drainage infrastructure, mitigating the risks associated with urban flooding and ensuring the safety of the citizens. It includes the rehabilitation of the stormwater drain in Karachi phase-II, the rehabilitation of Nehar-e-Khayam, and the rehabilitation of the existing sewerage system of Manzoor colony in District East.

In addition to the road and drainage projects, the budget also includes provisions for the construction of key civic amenities. One such project is the establishment of a civic centre at the Mula Fazal Auditorium Hall Chakiwara Road Liyari. This initiative aims to streamline the bureaucratic processes and provide a one-stop solution for various government-related matters.

The budget has also set aside funds for the construction of Bakhtiari youth centre as a sports complex and the construction of FB Area’s Allama Iqbal Park in the District Central.

Furthermore, the budget includes plans for the construction of the Korangi Causeway Bridge and an underpass at the Johar Chowrangi intersection. These infrastructure projects are expected to reduce bottlenecks on the roads and enhance overall connectivity within the city.

Mega schemes

S.No Mega schemes Location Estimated cost (Rs in millions) Estimated expenditure upto June 2023 (Rs in millions) Allocation for 2023-24 (Rs in millions)
1 Rehabillitation of various Roads and Allied works at SITE District Keamari 2393.949 2389.067 3.882
2 Rehabillitation of Sharah-e-Noor Jehan District Central 3367.735 1303.829 2063.906
3 Rehabilitation of Road from Shershah chowk to Mirza Adam Khan Road intersection District South 901.58 348.574 553.006
4 Rehabilitation of Road from Café piyala to Rashid Minhas Road District central 902.131 489.333 412.798
5 Reconstruction of Rafique Shaheed Road and Kala Pul Road from Shahr-e-Faisal to Main Korangi Road District Malir 526.266 208.461 317.807
6 Rehabilitation & widening of Road from Razaqabad to Sheedi Goth Power house District Malir 307.539 209.335 98.204
7 Rehabilitation of internal roads in surrounding Areas of Dr. ruth Pfau Civil Hospital District South 258.144 184.55 73.149
8 Rehabilitation of Chakiwara Road, Mehrab Khan Essa Road and Tennery Road Liyari Town 1500 866.454 633.546
9 Construction of Flyover and Underpass at Johar Chowrangi intersection District East 4225.601 2046.3 2179.301
10 Rehabilitation of water supply and sewerage system including E&M installation of pumping station of Each District Karachi Karachi 789.127 398.509 390.618
11 Constrution of Allama Iqbal Park at F.B Area District Central 250 0 250
12 Construction of Civic center at Mula Fazal Auditorium Hall, Chawkiwara Road District South 434.627 181.472 253.155
13 Reconstruction of Syed Raees Ahmed Jafri Road District central 712.93 374.5 338.43
14 Rehabilitation of Storm Water Drain i n Karachi Phase-II Karachi 999.967 125 874.967
15 Rehabilitation of Nehra-e-Khayam District South 499.993 0 124.998
16 Construction of Dual Carriageway Road from Nasir Brohi Hotel towards Mubarak village upto Coast Guard Picket District Keamari 440.85 0 220.425
17 Construction of Sport Complex - Bakhtiyari Youth Center District central 599.7 0 599.7
18 Rehabilitaion of Main Road in Sachal Goth District East 299.916 0 74.98
19 Rehabilitaion of existing sewerage system, Manzoor Colony District East 246.51 0 61.628
20 Construction of Korangi Causeway Bridge District Korangi 4677.551 0 3000
Total 24334.116 9125.384 12524.5

For the latest news, follow us on Twitter @Aaj_Urdu. We are also on Facebook, Instagram and YouTube.

karachi

sindh

Sindh budget

Comments are closed on this story.

Comments

Taboola

Taboola ads will show in this div